Location: Montney, BC

  • Pipeline System Expansion

    Pipeline System Expansion

    The Challenge

    British Columbia has stringent pipeline regulations and the geography presents harsh weather and steep/diverse terrain. Due to the project’s construction size, nearly 60 vendors were required over the 10+ month schedule. With various constructability issues, especially pertaining to hydrotesting, de-watering and purging operations, the Client required a team with experience and the right tools to complete the project.

    The Solution

    • CANUSA EPC provided a single point of contact for all 59 vendors
    • Designed and coordinated to safely cross large rivers while meeting all environmental regulations
      • Septimus NPS 8 sales gas and gathering pipeline loop (combined 9,800+ meters; river crossings)
      • Monias NPS 12 sales gas, NPS 6 natural gas and NPS 6 liquid pipeline constructions (combined 55,600+ meters)
      • Saturn NPS 16 sales gas pipeline construction (combined 23,900+ meters; river crossings)
    • Design of the pipeline pigging facilities for 900 ANSI system under CSA specifications
    • Daily, weekly and monthly project reporting including budget, schedule, safety and quality
    • Sweet natural gas and condensate pipelines were constructed as spare bi-directional lines for future production

    The Results

    • Improved capacity and flexibility of the gathering and sales pipeline system
    • NPS 16 sales gas pipeline connected the NPS 12 pipeline from existing gas plant
    • Transported sweet natural gas from the field to the existing gas plant – allowing for incremental gas production
    • Provided flexibility for Client logistics with bi-directional designs